Construction on the Center Street Underpass is progressing as scheduled. Crews are currently installing pile shoring to provide temporary structural support along the southwest side of the underpass, while also coordinating with the Railroad to accommodate its scheduled activities.
Cannon Builders, in coordination with construction engineering and inspection services provided by Civil Science, will proceed with concrete placement for the foundation footings and walls on both the southeast and southwest sides of the underpass. In addition, the project crane will be relocated to the east side of the site to begin construction activities in that area.
Pedestrian access will remain available throughout construction. The north pedestrian tunnel will remain open to ensure continued connectivity within the project area. Additional updates will be provided as the project progresses.
The City of Pocatello appreciates the continued patience and support of residents and local businesses as this important infrastructure project moves forward. Additional updates will be shared as construction progresses.