August 2, 2018
The contractor has been working on the subgrade and pouring the concrete curbing and sidewalks. All the concrete work will be done by the end of next week. The posts for the fence around the park have been installed but the rest of the fence will not be put up until they are ready for final grading.
July 3, 2018
The contractor has removed the existing fence and asphalt and is working on rough grading. They will be starting to pour the curb and gutter the end of this week and finish most of the sidewalks next week.