November 8, 2023
The pedestrian improvements project on E. Center is nearly complete. Only minor work related to a retaining wall remains. The project installed sidewalks and updated curb ramps to provide an unhindered path from 13th Ave to 18th Ave on Center Street.
September 26, 2023
The ADA Improvements on Center Street are in progress. Updated curbs and approaches have been poured. Asphalt will be patched this week and then sidewalks will be installed.