Water Pollution Control Facility Upgrades
November 8, 2023 Updates at the Water Pollution Control Facility are continuing. Current work includes masonry for mixing building, work on aeration basin #3 which […]

S 5th Ave and Jason Ave Project Complete
November 8, 2023 The project at S. 5th Ave and Jason Ave is complete, except for the installation of the flashing beacons. All the pavement […]

Center Street ADA Improvements
November 8, 2023 The pedestrian improvements project on E. Center is nearly complete. Only minor work related to a retaining wall remains. The project installed […]

Construction Begins on New Gravel Parking Lot and Boat Ramp
New large gravel parking lot and boat ramp going in on Batiste Road on the northwest side of the bridge by Water Pollution Control (WPC). […]

Replacing Garrett Way Water Main in 8-Week Project
Beginning Monday, October 9, 2023, crews from the City of Pocatello Water Department will be replacing the water main line on Garrett Way, Madison Ave., […]

S 5th Ave and Jason Street Nearing Completion
September 7, 2023 The project on S. 5th and Jason is nearly complete. The project has repaired the asphalt and will begin striping.

Transmission Line Replacement for 5 Million Gallon Tank
August 15, 2023 Paving of Fore Road has begun. Construction on the project will continue into the fall. February 27, 2023 The contractor continues pipe […]

Curbing at S 5th Ave and Jason Street
August 14, 2023 The ADA and pedestrian access project at S. 5th Ave/Jason Street has completed the demolition phase. Tear out of old infrastructure for […]

Curb and Gutter on Pocatello Creek Road
August 11, 2023 Crews are working on curb and gutter on Pocatello Creek Road.

Striping Underway at the Hawthorne and Quinn Intersection
July 28, 2023 The intersection at Hawthorne and Quinn has been paved and striping has begun.

Hawthorne Road and West Quinn Road Set to Reopen
July 24, 2023 Crews have been working diligently on the Hawthorne Road and West Quinn Road intersection, with most of the project expected to be […]

Well Replacement Project
Well drilling has been completed for replacement of well 2R and well 22R. Well pump testing and final installation of casing screens will be completed […]